Structured Cabling

Structured cabling installation and handover

Workmanship and documentation checks before practical completion.

Zi-On
Site
Date
Technician
Reference

Installation

  • Containment complete, lids fitted, fill within limits
  • Separation from mains power maintained; crossings at 90°
  • Bend radius and pulling tension respected (no kinks or crush)
  • Hook-and-loop ties used; no overtightened ties
  • Service loops left in comms rooms
  • All penetrations firestopped and recorded

Terminations and racks

  • One wiring scheme (T568A or T568B) throughout
  • Untwist within 13 mm at every termination
  • Racks bonded to the telecom earth bar; screened panels bonded
  • Cable managers fitted; cords dressed neatly
  • Blanks fitted to unused faceplate positions

Labelling (TIA-606)

  • Every cable labelled at both ends within 300 mm of termination
  • Outlets, panels, racks, and rooms labelled to the agreed scheme
  • Labels printed, legible, and matching the records

Testing and records

  • Every copper link certified to the specified category (no marginal passes if excluded)
  • Every fibre link OLTS tested at both wavelengths; loss within budget
  • Native test files and PDF summary showing 100% pass
  • As-built drawings, rack elevations, and cable schedules
  • Manufacturer warranty submitted

Notes / defects

Technician signature

Client / supervisor signature